Tan An City accelerates compensation payment for National Highway 62 – Hung Vuong intersection project

 

Currently, Tan An City (Long An province) is urgently speeding up the payment of compensation for the project of National Highway (NH) 62 – Hung Vuong intersection project.

As for the remaining households who have not yet agreed to the site clearance policy, the City People’s Committee continues to advocate, explain, create consensus and reach a general consensus. The City People’s Committee has approved the bidding documents, the units are organizing construction bidding according to regulations for 3 bidding packages (construction, supervision consultancy, electrical relocation), expected to award Bidding before December 18.

In addition, the city will organize to commend and reward organizations and individuals who have consensus and well implemented the implementation of this project, especially households who well abide by the policy of the State, contribute to accompanying the the development of the city.

In the direction of 2022, the city will fully implement the site clearance and construction work for the NH 62 – Hung Vuong intersection project according to the approved plan.

It is known that the city also organized to pay compensation for 99 out of 99 households, reaching 100 percent of the project of Ward 2 Park – Phase 2 before. When the project is implemented, there is high consensus and agreement from the people. In terms of progress, implementation steps, compensation, support, and resettlement procedures have basically reached the set schedule. The total cost of site clearance is nearly 200 billion VND, arranging resettlement for 84 households whose houses and land have been cleared. The project is finalizing according to regulations and started construction in November 2021. The whole area after the complete investment creates a clean, beautiful landscape; spacious features, highlight for urban city.

Chairman of the People’s Committee of Tan An City – Nguyen Quang Thai said that, for the construction of works in the city, on the basis of the direction of the Standing Committee of the City Party Committee, the City People’s Committee has developed a specific plan for each project with the highest political determination to clear the ground, create consensus from the people to ensure the handover of the site according to the construction schedule of the projects./.

 

Source: LONG AN PORTAL

 